Week of 2/5/2008 - 2/11/2008

Week 4

-Finish working circuit with hack remote (make robust to work with soft switch)
-Get working prototype with microcontroller, set up meeting with pcb designer
-Buy first round of fabrics with Rebecca

Week of 2/12/2008 - 2/18/2008

Week 5

-Meet with Rosie to document schematic/eagle file of arduino circuit to make pcb
-Meet with Leif to discuss leadtime of pcb ordering
-Make thorough questionaire for user testing for riders on Mt. Schweitzer
-Finish working hack remote with real glove to test in Idaho

Week of 2/19/2008 - 2/25/2008

Week 6

-Begin draping dressform
-Begin midterm presenations/outline
-Begin second prototype with remote hack based on research results (try belt/jacket version)
-Start website/Start research paper

Week of 2/26/2008 - 3/03/2008

Week 7

-Work on website more/Begin market research
-Sewing, sewing, sewing (work at parsons to begin muslin for suit)
-User research, second draft based on first trial's results
-Continuous circuit testing

Week of 03/04/2008 - 3/10/2008

Week 8

-Begin muslin, test with soft circuit (both wrap wire and conductive fabric)
-Solder/Test/Program pcb *(should be back by this point}
-Continue work on modification garments
-Website work
-Create outline for paper

Week of 03/11/2008 - 3/17/2008

Week 9

-Finish muslin
-Continue modification garments
-User testing on first version of modification garments
-Finish website
-Begin formal paper

Week of 03/18/2008 - 3/24/2008 (SPRING BREAK/OUT OF COUNTRY)

Week 10

-Finish muslin/Begin custom garments with PBC
-Continue modification garments
-User testing on first version of modification garments
-Continue paper/begin formal documentation

Week of 03/25/2008 - 3/31/2008

Week 11

-Continue/Finish modification garments
-Continue custom garments -User testing on first version of modification garments
-Finish Website
-Continue paper/begin formal documentation

Week of 4/01/2008 - 4/07/2008

Week 12

-Finishing touches on all garments
-Catch up week. Safety week for complications
-Continue paper, begin outline for presentation of thesis

Week of 4/08/2008 - 4/14/2008

Week 13

-Finish all garments
-Finish documentation/finish paper
-Begin presentation/reflection

Week of 4/15/2008 - 4/21/2008

Week 14

-Finish all garments/Photoshoot/Media assets if necessary
-Continue on presentation
-Revise paper/Revise webdesign/(After getting feedback)

Week of 4/22/2008 - 4/28/2008

Week 15

-Finish everything, extra week for complications
-
-